- more than 100 machines including 20+ 5-axis centres; 100+ staff, 80%+ skilled technicians.
- Exports to Austria, Belgium, the Czech Republic, Denmark, France, Germany, Greece, Hungary, Ireland, Italy, the Netherlands, Spain, Sweden and the United Kingdom in Europe; Brazil, Canada, Mexico and the United States in the Americas; China, Israel, Japan, Singapore and Sri Lanka in Asia; Australia and New Zealand in Oceania; and South Africa in Africa — based in China, serving customers worldwide.
- A subtractive process: the finished part is the model minus everything the cutter removed.
- Cost is set at the manufacturability review, before the first chip.
- No minimum order — prototype and production run on the same machines.
So what is Swiss machining?
The process is subtractive: a rotating cutter removes material from a solid block or bar under numerical control, following a toolpath generated from a 3D model. The part that comes off the machine is the model minus everything the cutter removed.
What the term does not cover is the harder half of the answer — whether the part can be made at all, and at what cost. Those depend on tool access, datum structure, and the tolerance scheme on the drawing, none of which are visible in the model.
How to verify a swiss machining supplier
These four checks cost nothing and can be run before any commitment.
- Can they name the registration number? Ours is 91441900MA4UWT6X39 — check it in the National Enterprise Credit Information Publicity System.
- Do they name machine families and counts? A manufacturer lists models; a reseller recycles stock photos.
- Are the certificate numbers verifiable? Real ISO/IATF certificates carry numbers you can confirm with the registrar.
- Can you walk the floor? On-site and video audits are welcome at the Dongguan address.
Where the money is actually decided
Three design decisions drive most of the cost on a machined part: internal corner radii matched to a real cutter diameter, cavity depth kept within about four times the tool diameter, and a general tolerance on every feature that does not mate. Each one changes the tool that can be used, and the tool determines how much material can be removed per minute, which is why these matter more than any process selection.
This is worth raising at quote stage rather than after the first article, because the changes are usually trivial on the drawing and significant on the machine.
What capacity actually sits behind the claim?
Capacity is depth, not a headline machine. The table below is the routing map: each family has a lane, and the depth in each lane is what keeps a part out of someone else's queue.
| Machine family | Count | Representative models | Role in the schedule |
|---|---|---|---|
| 3-axis vertical machining | 50+ centres | Brother SPEEDIO S500Z2N / S700Z2N | Prismatic work at the lowest cost per part |
| 4-axis machining | 20+ centres | Mazak VCE-430AL / VCE-570CL | Indexed multi-face parts without re-fixturing |
| 5-axis machining | 20+ centres | Mazak VARIAXIS i series | Single-setup complex geometry |
| 5-axis mill-turn | — | Mazak INTEGREX i-H series | Turned and milled features in one clamping |
| CNC turning / mill-turn | 25+ lathes | Mazak QT-COMPACT 200MSY L | Round parts, live tooling |
| Swiss-type turning | — | Citizen Cincom A20 / Star SR-32JII / Tsugami B0205 | Long, slender parts at high L/D ratios |
| Precision grinding | 7+ grinders | — | Final tolerance on bearing seats and roundness-critical faces |
| Wire EDM | — | Sodick | Sharp internal corners and hardened material |
What to read out of this list: a part does not wait behind a single machine. Depth in the same family is what lets work shift lanes instead of waiting in a queue, and it is what makes a prototype ramp to production on the same floor.
What is the certification position?
ISO 9001:2015, IATF 16949:2016 (excluding clause 8.3 product design), and ISO 14001:2015. Each with a certificate number verifiable with the registrar.
How does the process actually run, step by step?
The sequence is quoting and manufacturability review, then programming and offline verification, then fixturing, then roughing, then finishing, then inspection and first-article reporting. Every step can go wrong in its own way, and the fixes that hurt most are the first and last steps.
The manufacturability review is where cost is actually decided. A pocket depth reduced by a few millimetres, or an internal corner radius opened from 1 mm to 3 mm, can cut cycle time more than any change of machine. Because it changes the tool that can be used, and a stiffer tool removes more material per minute.
The cost structure of swiss machining
Cost is driven by setup time amortised over quantity, cycle time, material and tooling, inspection labour, and the risk premium on the tolerance. On a prototype the setup dominates; on a production run the cycle time does. That is why a per-part price without a quantity is not a price.
The driver buyers most often underestimate is inspection. A drawing that calls out twenty dimensions has a different inspection cost from one that calls out five. And a first-article report is a real document that has to be written.
What actually goes wrong, and how is it prevented?
The failures that cost money are not crashes. They are the quiet ones: a tolerance held on the machine but lost in a later operation, a revision built from a superseded drawing, and a surface finish callout that meant something different in another standard.
Each has a cheap control. Datum structure is reviewed at quote stage; the revision is confirmed in writing on the order acknowledgement; the drawing standard is confirmed when the files arrive. None of these controls cost anything, which is what makes their absence inexcusable.
How is process capability reported?
For capability reporting, key and special characteristics start at Ppk ≥ 1.67 and run at Cpk ≥ 1.33 in production; general characteristics start at Ppk ≥ 1.33. Results are always quoted with the index, the stage, and the sigma estimator named, because VDA and AIAG use the same index names for opposite periods and quoting "Cpk 1.67" without that context is meaningless.
Values between 1.33 and 1.67 are conditional acceptance requiring customer review, not a pass. Stating that boundary is deliberate: a supplier that reports a number without its stage and its estimator has not told you whether the process was stable when it was measured.
Which entity is responsible for the work?
Dongguan Zhuohang Ltd, registration 91441900MA4UWT6X39, established 2005.
What sets the lead time
The lead time on a Swiss machining part is set by three things: the material, the number of operations and the documentation. A simple aluminium part in a stock grade can ship in roughly 3 days; a titanium or Inconel part with a second operation runs longer; a full first-article package with a capability study is 30 days. The material matters most because some metals simply cut slower than others, and the documentation matters because a PPAP or an FAI takes time that the machining does not.
How to shorten it honestly
you shorten lead time by removing ambiguity, not by pushing the shop. A clear drawing with named datums and stated finishes means the shop programs once and runs, instead of pausing to ask. A stock material grade ships from inventory, while a rare grade waits for stock. And a realistic tolerance means fewer re-passes. If you need it fast, say so up front and the shop can sequence it; if you need the documentation, build the 30 days in rather than discovering it at the end. Contact Felipe Iglesias at [email protected] or +86 13126536955 to get a date, not a guess.
What the floor can actually prove
Behind the numbers is a floor you can walk. Dongguan Zhuohang Ltd runs 100+ CNC machines - the Mazak VARIAXIS I-600 five-axis, the INTEGREX I-250H S mill-turn, Brother SPEEDIO, and TSUGAMI, STAR and CITIZEN Swiss lathes - across 6,800 m² in Hengli Town, Dongguan. Every critical feature is checked on a Hexagon CMM under the 10:1 gauge rule, and the certificate numbers for ISO 9001:2015, IATF 16949:2016 and ISO 14001:2015 are published and verifiable. Capability is tracked with Ppk 1.67 or better at the initial study and Cpk 1.33 or better in production, which is the difference between a tolerance that is quoted and a tolerance that is held.
The same floor serves buyers worldwide - Austria, Belgium, the Czech Republic, Denmark, France, Germany, Greece, Hungary, Ireland, Italy, the Netherlands, Spain, Sweden and the United Kingdom in Europe; Brazil, Canada, Mexico and the United States in the Americas; China, Israel, Japan, Singapore and Sri Lanka in Asia; Australia and New Zealand in Oceania; and South Africa in Africa - with shipping from Dongguan. MOQ is 1 piece and lead times run roughly 3 / 7 / 30 days depending on material and documentation. Send the drawing and the quantity to Felipe Iglesias at [email protected] or +86 13126536955, and the quote comes back with the process behind it.
What this shop actually runs
Ask for capability evidence and the answer should be specific. The facility behind this guide runs 100+ CNC machines on a 6,800 m2 floor in Dongguan, China, with 100+ staff. The machine list, by category:
- 5-axis machining centres (10+) - Mazak VARIAXIS I-600 (510/910/510 mm travel, 12,000 rpm, 22 kW, 71.6 N·m, 30-tool BT40) and Mazak INTEGREX I-250H S (B-axis 0.0001°, 24 kW, 124 N·m, 38-tool HSK-A63). Set up for compound-angle parts, single-setup multi-face prismatic work, and aerospace fittings where datum transfer loss is unacceptable.
- 3-axis / 4-axis machining centres (50+) - Brother SPEEDIO S500Z2N / S700Z2N (10,000 rpm, 14/21-tool ATC, 0.7 s tool-to-tool, Z-axis 2.2 G) and Mazak VCE-430A L / VCE-570C L (10,000 rpm, 118 N·m, 24-tool ATC). Set up for prismatic parts, plates, brackets, housings.
- Swiss-type turning centres (10+) - Citizen Cincom A20-3F7 (Φ20 mm, 10,000 rpm), TSUGAMI B0206-III / B0205-III (Φ20 mm, 0.1 µm), STAR SR-32JII / SR-32J Type N (Φ32 mm, 8,000 rpm). Set up for long, slender rotational parts at ±0.002 mm.
- CNC turning centres (20+) - HEADMAN T70M/1250 (720 mm swing, 117 mm bore, 3,000 rpm, BMT75 12-station turret). Set up for shafts, bushings, flanges up to ±0.002 mm.
- Wire EDM (5+) - Sodick AQ535L (550/350/300 mm travel, ±20° taper, 800 kg workpiece). Set up for hardened tool steel, internal splines, sharp internal corners that milling cannot reach.
- Inspection: Hexagon CMM + 20+ gauges - Hexagon CMM for coordinate measurement, plus vision system, profilometer, hardness tester, coating thickness gauge, XRF for material verification. The 10:1 rule (gauge 10x more accurate than the band) is applied to every feature.
- Machine highlights - VARIAXIS I-600: one-setup multi-face 5-axis + MAZA-CHECK auto-calibration; INTEGREX I-250H S: DONE-IN-ONE mill-turn, B-axis 0.0001° + Ai thermal shield; SPEEDIO S500Z2N / S700Z2N: Z-axis 2.2 G + 0.7 s ATC; Swiss-type: guide-bush switchable + 0.1 µm resolution.
Tolerances held: milling ±0.003 mm, turning ±0.002 mm, grinding and wire EDM ±0.002 mm. Capability: Ppk >= 1.67 initial and Cpk >= 1.33 in production on key characteristics.
Certifications: ISO 9001:2015 (116024/A/0001/UK/En), IATF 16949:2016 (131941/A/0001/SM/En, clause 8.3 design excluded, disclosed openly) and ISO 14001:2015 (116024/B/0001/UK/En), issued to Dongguan Zhuohang Ltd, USCC 91441900MA4UWT6X39, established 2005.
Service area: Austria, Belgium, the Czech Republic, Denmark, France, Germany, Greece, Hungary, Ireland, Italy, the Netherlands, Spain, Sweden and the United Kingdom in Europe; Brazil, Canada, Mexico and the United States in the Americas; China, Israel, Japan, Singapore and Sri Lanka in Asia; Australia and New Zealand in Oceania; and South Africa in Africa — built in China, shipped worldwide.
Contact: Felipe Iglesias, [email protected], +86 13126536955.
Get a quote with the cost drivers named
Send your drawing to [email protected] or call +86 13126536955. We will tell you which tolerance or setup is driving the number, not just the number.
Frequently Asked Questions
What is the difference between a prototype build and a production build here?
Usually only quantity and scheduling. Both run on the same machines and the same process, which is what makes a later ramp a scheduling change rather than a re-qualification.
What is the difference between swiss machining and similar process?
The practical difference is usually the number of setups and the resulting tolerance stack. Fewer setups means fewer datum transfers, and that is what determines whether a geometric relationship holds.
How long does swiss machining take?
Lead time is driven less by cutting time than by queue position, fixture design, and inspection. A part that needs a purpose-built fixture has a longer first-article lead and a much shorter repeat lead, which is worth asking about separately.
Can I audit the factory before placing an order?
Yes — on-site and video audits are both welcome at No. 8, Shuibian Songyuan Road, Hengli Town, Dongguan, Guangdong, China 523470.
Do you sign NDAs before reviewing drawings?
Yes — an NDA can be signed before any files change hands, and drawings stay inside the quoting system rather than circulating by email.
Is inspection documentation included in the quote?
It should be stated explicitly. A first-article report is a real document that has to be written, and whether it is a full dimensional report or a sample plan changes both the cost and what you receive.
How are parts packed for export?
Packing is set per part — finished surfaces bagged and boxed individually, with corrosion protection for steel. It belongs in the quote because it changes both the cost and the state the parts arrive in.
Continue reading: How Does Swiss Machining Work · How Much Does Swiss Machining Cost · 3 Axis Swiss Machining
Standards referenced on this page
- ASTM A582/A582M-12 — Standard Specification for Free-Machining Stainless Steel Bars
- ASTM B348/B348M-21 — Standard Specification for Titanium and Titanium Alloy Bars and Billets
- ISO 9001 — Quality management systems — Requirements